Project Description

Client: Public Works Authority (Ashghal)
Location: Duhail Zone 30
Year Completed: Not Provided
Value: $51,609,186.26

Construction of dual carriageways, service roads, and parking facilities around ISF Camp with comprehensive works including earthworks, sub-base, pavement construction, kerbing, and ITS network installation.

The Challenges

Working within a sensitive camp environment while adhering to strict safety protocols.

This Project includes the construction of dual carriageway roads, service roads & parking

The work consists of Site Clearance, Earthworks, Sub-base, pavement construction, Kerbing works, Traffic Signs, traffic signals, road Markings, street lighting, storm water drainage, provision of ducts, ITS (intelligent Transportation System),

  • Earthworks: 132,000 Tons
  • Sub-base & Road Base: 100,881 Tons
  • Flexible Surfacing: 179,265 Tons
  • Kerbs: 82,125m2
  • Interlocks:208,000m2
  • Traffic Signs & Road Marking: 798 Nos.
  • Streetlighting
  • ITS Network
  • Interceptor Sewer Micro tunneling Pipe Jacking: 2,772m2