Project Description
Client: Public Works Authority (Ashghal)
Location: Duhail Zone 30
Year Completed: Not Provided
Value: $51,609,186.26
Construction of dual carriageways, service roads, and parking facilities around ISF Camp with comprehensive works including earthworks, sub-base, pavement construction, kerbing, and ITS network installation.
The Challenges
Working within a sensitive camp environment while adhering to strict safety protocols.
This Project includes the construction of dual carriageway roads, service roads & parking
The work consists of Site Clearance, Earthworks, Sub-base, pavement construction, Kerbing works, Traffic Signs, traffic signals, road Markings, street lighting, storm water drainage, provision of ducts, ITS (intelligent Transportation System),
- Earthworks: 132,000 Tons
- Sub-base & Road Base: 100,881 Tons
- Flexible Surfacing: 179,265 Tons
- Kerbs: 82,125m2
- Interlocks:208,000m2
- Traffic Signs & Road Marking: 798 Nos.
- Streetlighting
- ITS Network
- Interceptor Sewer Micro tunneling Pipe Jacking: 2,772m2