Project Description
Client: Al Jaber Engineering / Ashghal
Location: Wadi Aba Seleel
Year Completed: Not Provided
Value: $12,626,554.57
Advance grading and temporary road construction including asphalt base course, prime coat, and road marking works.
The Challenges
Achieving precise grading and high-quality pavement installation under challenging conditions.
Advance grading and temporary roads. Asphalt base course and Prime coat; Supply and lay of asphalt base Course & Spraying of prime coat and Road marking works.
- Asphalt Base Course Type-1 (90mm) 74,096 Tons
- Intermediate Course Type-1 (60mm) 5,481 Tons
- Base Course Type-1 (80mm) 26,356 Tons
- Wearing Course (50mm) 31,727 Tons
- Laying of Sub-base (200mm) 114,604 Tons
- Prime Coat 192 Tons Tack Coat 183 Tons