Project Description
Client: Council for Development and Reconstruction (CDR)
Location: Beirut
Value: $8,971,076.22
Performed Works
- Earthworks 38,000m3,
- Granular subbase 7600m3
- Asphalt works 41,000Ton
- Concrete works 1100m3 and reinforcing steel to 800Ton.
- Tiling 24000m2
- Reinforced soil walls structure
- Expansion joints: Replacement 7 20lm
- Movement rang 80mm
- Reflective studs 2600pcs
- Construction of a storm water drain age network
- Safety barriers 2800lm
- Guard rails
- Curbstones 18,000lm
- Road marking 3750m2
- Traffic safety