Screenshot 2025-02-24 at 12.20.37 AM

Project Description

Client: Council for Development and Reconstruction (CDR)
Location: Beirut
Value: $8,971,076.22

Performed Works

  • Earthworks 38,000m3,
  • Granular subbase 7600m3
  • Asphalt works 41,000Ton
  • Concrete works 1100m3 and reinforcing steel to 800Ton.
  • Tiling 24000m2
  • Reinforced soil walls structure
  • Expansion joints: Replacement 7 20lm
  • Movement rang 80mm
  • Reflective studs 2600pcs
  • Construction of a storm water drain age network
  • Safety barriers 2800lm
  • Guard rails
  • Curbstones 18,000lm
  • Road marking 3750m2
  • Traffic safety